(290) What is the MAIN purpose of a change control/management system?

A. Notify all interested parties of the completion of the change.
B. Ensure that the change meets user specifications.
C. Document the change for audit and management review.
D. Ensure the orderly processing of a change request.

Correct Answer: C


Explanation/Reference: