(96) Which of the following is the GREATEST concern when an organization’s backup facility is at a warm site?
A. Timely availability of hardware
B. Availability of heat, humidity and air conditioning equipment
C. Adequacy of electrical power connections
D. Effectiveness of the telecommunications network


Explanation:
A warm site has the basic infrastructure facilities implemented, such as power, air conditioning and networking, but is normally lacking computing equipment. Therefore, the availability of hardware becomes a primary concern.